Proceed external review (Fire Dept)
(last modified: 14/08/2019)

Espera hasta paso siguiente

1 day  -  3 days

Contact details

Entity in charge

Maseru Fire Brigade

Constitution Rd, Maseru, Maseru
Tel: +266 22317263

Unit in charge

Maseru Fire Brigade

Mon: 08:00 - 12:45, 14:00 - 16:30
Tue: 08:00 - 12:45, 14:00 - 16:30
Wed: 08:00 - 12:45, 14:00 - 16:30
Thu: 08:00 - 12:45, 14:00 - 16:30
Fri: 08:00 - 12:45, 14:00 - 16:30

Person in charge

'Muso Lehlokoa

Senior Inspector (Officer command fire & Rescue)
Tel: +266 50484985
Email: lehlokoa.muso@yahoo.com

Requirements

1. 01 - Libre deuda de patente
Architectural drawing (original)

Time frame

Waiting time until next step: Min.   1 day - Max.   3 days

Additional information

Application is received by mail at the Fire Brigade, and the fire department is only interested on the architectural drawing to check the fire protection.

The reviewers log on to the MCC system to see if there are pending applications to be reviewed.

There are no standards or laws in Lesotho in terms of fire protection, they rely on South African national laws in terms of fire protection and standards.

The fire department will only approves the architectural drawing if they are satisfied with the fire protection of the building, if not they will make recommendations and send back report to MCC.